The Happiness Meter

Mon, 2008-06-23 04:01
As part of any iteration review / planning meeting there should be a section where everybody involved talks about how they felt the last iteration went, what they thought stood in the way, what they though went particularly well and suchlike.

We find that as the project goes on, and the team gets more and more used to each other, this tends to pretty much always dissolve into everyone going "alright I suppose", "yeah fine".

Obviously, this isn't ideal and will tend to mean that you only uncover problems in the project when they've got pretty serious and nerves are pretty frayed.

This is where "The Happiness Meter" comes in.

Instead of asking the team if they think things are going OK and having most people respond non-committally, ask people to put a value against how happy they are with the last iteration's progress. Any range of values is fine, just as long as it has enough levels in it to track subtle movements. I'd go with 1-10.

You don't need strict definitions for each level, it's enough to say '1 is completely unacceptable, 5 is kinda OK, 10 is absolute perfection'.

At some point in the meeting, everyone in the team declares their level of happiness. When I say everyone, I mean everyone: developers, customers, XP coaches, infrastructure guys, project managers, technical authors, absolutely everyone who is valuable enough to have at the iteration review meeting should get a say.

In order to ensure that everyone gets to provide their own thought, each person writes down their number and everyone presents it at the same time. The numbers are then taken recorded and a graph is drawn.

From the graph we should be able to see:
  1. The overall level of happiness at the progress of the project.

  2. If there is any splits / factions in the interpretation of the progress.




If the level of happiness is low, this should be investigated; if there are any splits, this should be investigated; and just as importantly - if there are any highs, this should be investigated. It's good to know why things go well so you can duplicate it over the next iteration.

Factions tend to indicate that one part of the team has more power than the rest and the project is skewed into their interests rather than those of the team as a whole.

You may want to split the graph into different teams (customer / developer) if you felt that was important, but I like to think of us all as one team on the same side...

All said and done, the graph isn't the important bit - the discussion that comes after the ballot is the crucial aspect. This should be a mechanism for getting people to talk openly about the progress of the project.

UPDATE: Someone at work suggested a new name that I thought I should share: The Happy-O-Meter.

Ideas for improving innovation and creativity in an IS department

Sat, 2008-06-21 04:49
At our work we've set up a few 'action teams' to try to improve particular aspects of our working environment.

The team that I'm a member of is responsible for 'Innovation and Creativity'.

We're tasked with answering the question "How do we improve innovation and creativity in IS?" - How we can foster an environment that encourages innovation rather than stifles it.

As a bit of a background, the company is a a medium sized (2,500 plus employees) based mainly in the UK, but recently spreading through the world, the vast majority of whom are not IS based. The IS department is about 100 strong and includes a development team of 25 people. It's an SME at the point where it's starting to break into the big-time and recognises that it needs to refine its working practices a little in order to keep up with the pace of expansion.

We met early last week and have put together a proposal to be taken to the senior management tier. I get a feeling it will be implemented since our team included the IS Director (you don't get any senior in our department), but you never know what'll happen.

I figured it might be interesting to record my understanding of the plan as it stands now, and then take another look in 6 months time to see what's happened to it...

We decided that in order to have an environment that fosters creativity and innovation you need:

Freedom:

Time for ideas for form, for you to explore them, and then to put them into practice.

Stimulus:

Outside influences that that can help to spark those ideas off - this may be from outside the organisation, or through cross-pollination within it.

Courage:

The conviction to try things, to allow them to fail or succeed on their own merit - both on the part of the individual and the organisation as a whole.

Natural Selection:

The need to recognise success when it happens, to take it into the normal operation of the business and make it work in practice. Also, the need to recognise failure when it happens, and stop that from going into (or continuing to exist within) the team.

Recognition:

When we have a good idea, the people involved need to be celebrated. When we have a bad idea, the people involved DO NOT need to be ridiculed.

Refinement:

The initial ideas aren't always the ones that are successful, it's the 4th, 5th or 125th refinement of that idea that forms the breakthrough. We need to understand what we've tried, and recognise how and why each idea has failed or succeeded so we can learn from that.



We put together some concrete ideas on how we're going to help put these in place - and bear in mind that this isn't just for the development team, this is for the whole of the IS department - development, project management, infrastructure, operations, service-desk, even the technology procurement...

Curriculum:

A position set up that will be responsible for defining / tracking a curriculum for each job role in the department.

Obviously this will be fed by those people that currently fulfil the roles, and will involve things ranging from ensuring the process documentation is up to scratch, through specifying reading lists (and organising the purchasing of the books for the staff) and suggesting / collecting / booking conferences, training courses and the like that might be of use.

This takes the burden of responsibility away from the staff and managers - all you need is the idea and someone else will organise it and ensure it's on the curriculum for everyone else to follow up.

IdeaSpace (TM ;-) ):

A forum for the discussion of ideas, and collection of any documentation produced on those ideas and their investigation. This will (hopefully) form a library of past investigations as well as a stimulus for future ones. Everyone in the department will be subscribed to it.

Lab days:

Every employee is entitled to 2 days a month outside of their normal job to explore some idea they might have. That time can be sandbagged to a point, although you can't take more than 4 days in one stint. Managers have to approve the time in the lab (so that it can be planned into existing projects) and can defer the time to some extent, but if requests are forthcoming they have to allow at least 5 days each rolling quarter so that the time can't be deferred indefinitely.

Whilst the exact format of the lab is yet to be decided, we're aiming to provide space away from the normal desks so that their is a clear separation from the day job and lab time. People will be encouraged to take time in the lab as a team as well as individually. Also, if we go into the lab for 3 days to find that an idea doesn't work, that idea should still be documented and the lab time regarded as a success (we learnt something)

Dragon's Den:

Gotta admit, I'm not sure about some of the connotations of this - but the basic idea is sound. Coming out of time in the Lab should be a discussion with peers about the conclusion of the investigation in a Dragon's Den format. This allows the wider community to discuss the suitability of the idea for future investigations, or even immediate applicability. One output of this meeting may be the formalisation of conclusions in the IdeaSpace.

Press Releases:

The company is already pretty good at this, but when something changes for the better we will ensure that we celebrate those changes and, even for a day, put some people up on pedestals.

None of the above should be seen as a replacement for just trying things in our day to day job - but the idea is that these things should help stress to the department that change and progress are important aspects of what we do, and that we value it enough to provide a structure in which big ideas can been allowed to gestate. Cross pollination and communication should just form part of our normal day job anyway, and we should ensure that our project teams are cohesive and communicate freely amongst and between themselves.

Also, an important factor in the success of the above has to be the format of the Dragon's Den - if it is in any way imposing or nerve-racking then the idea is doomed to failure. As soon as people feel under pressure to justify themselves then the freedom disappears.

I'm quite excited by the prospect of putting these ideas into practice, and I wonder exactly where we'll end up.

I'll keep you all posted.

Things I believe in

Sat, 2008-03-29 07:35
  • It's easier to re-build a system from its tests than to re-build the tests from their system.

  • You can measure code complexity, adherence to standards and test coverage; you can't measure quality of design.

  • Formal and flexible are not mutually exclusive.

  • The tests should pass, first time, every time (unless you're changing them or the code).

  • Flexing your Right BICEP is a sure-fire way to quality tests.

  • Test code is production code and it deserves the same level of care.

  • Prototypes should always be thrown away.

  • Documentation is good, self documenting code is better, code that doesn't need documentation is best.

  • If you're getting bogged down in the process then the process is wrong.

  • Agility without structure is just hacking.

  • Pairing allows good practices to spread.

  • Pairing allows bad practices to spread.

  • Cycling the pairs every day is hard work.

  • Team leaders should be inside the team, not outside it.

  • Project Managers are there to facilitate the practice of developing software, not to control it.

  • Your customers are not idiots; they always know their business far better than you ever will.

  • A long list of referrals for a piece of software does not increase the chances of it being right for you, and shouldn't be considered when evaluating it.

  • You can't solve a problem until you know what the problem is. You can't answer a question until the question's been asked.

  • Software development is not complex by accident, it's complex by essence.

  • Always is never right, and never is always wrong.

  • Interesting is not the same as useful.

  • Clever is not the same as right.

  • The simplest thing that will work is not always the same as the easiest thing that will work.

  • It's easier to make readable code correct than it is to make clever code readable.

  • If you can't read your tests, then you can't read your documentation.

  • There's no better specification document than the customer's voice.

  • You can't make your brain bigger, so make your code simpler.

  • Sometimes multiple exit points are OK. The same is not true of multiple entry points.

  • Collective responsibility means that everyone involved is individually responsible for everything.

  • Sometimes it's complex because it needs to be; but you should never be afraid to check.

  • If every time you step forward you get shot down you're fighting for the wrong army.

  • If you're always learning you're never bored.

  • There are no such things as "Best Practices". Every practice can be improved upon.

  • Nothing is exempt from testing. Not even database upgrades.

  • It's not enough to collect data, you need to analyse, understand and act upon that data once you have it.

  • A long code freeze means a broken process.

  • A test hasn't passed until it has failed.

  • If you give someone a job, you can't guarantee they'll do it well; If you give someone two jobs you can guarantee they'll do both badly

  • Every meeting should start with a statement on its purpose and context, even if everyone in the meeting already knows.

A reading list for our developers

Tue, 2008-03-25 12:54
An idea I'm thinking of trying to get implemented at our place is a required reading list for all our developers. A collection of books that will improve the way that developers think about their code, and they ways in which they solve problems. The company would buy the books as gifts to the employees, maybe one or two every three months.

Some questions though:

  • Is it fair for a company to expect its employees to read educational material out of hours?

Conversely:
  • Is it fair for an employee to expect to be moved forward in their career without a little bit of personal development outside the office?


If anyone has any books out there that they'd recommend - please let me know. Otherwise, here's my initial ideas - the first three would be in your welcome pack:

Update:Gary Myers came up with a good point, being that any book should really be readable on public transport. That probably rules out Code Complete (although I read it on the tube, I can see that it's a little tricky), but Design Patterns and Refactoring to Patterns are small enough I reckon.

Unfortunately, Code Complete is a really good book that gives a lot of great, simple, valuable advice. Does anyone out there have any other suggestions for similar books?

Update 2:Andy Beacock reminded me of Fowler's Refactoring, which really should also make the list.

Update 3:The development team have bought into the idea and the boss has been asked. In fact, I'm pretty pleased with the enthusiasm shown by the team for the idea. I can't see the boss turning it down. Interestingly though, someone suggested that Code Complete go onto the list...

In this order:


Ruled out because of their size:

Database Build Script "Greatest Hits"

Tue, 2007-09-04 09:54
I know its been a quiet time on this blog for a while now, but I've noticed that I'm still getting visitors looking up old blog posts. It's especially true of the posts that relate to "The Patch Runner". Many of them come through a link from Wilfred van der Deijl, mainly his great post of "Version control of Database Objects". The patch runner is my grand idea for a version controlled database build script that you can use to give your developers sandbox databases to play with as well as ensuring that your live database upgrades work first time, every time. It's all still working perfectly here, and people still seem to be interested, so with that in mind I've decided to collate them a little bit. basically provide an index of all the posts I've made over the years that directly relate to database build scripts, sandboxes and version control. So, Rob's database build script 'Greatest Hits': All of the posts describe processes and patch runners that are very similar to those that I use in my work every day. I started playing with these theories over 3 years ago now and there is no way I'd go back to implement database upgrades the way I did before. However, I'd LOVE to hear ideas on how things can be improved. I'd be amazed if my three year old thinking was still up to date! Technorati Tags: , , , , ,

Wow

Mon, 2007-08-20 10:52
And you think software patents are bad...

China Regulates Buddhist Reincarnation

Problems with CVS removes?

Fri, 2007-07-20 10:58
Accidently removed a file in CVS that you want to keep?

Sounds like a stupid question, because when you know the answer to this problem it just seems blindingly obvious,
but what if you've issued a 'remove' against a file in CVS and before you commit the remove you decided that you
made a mistake and still want to keep it?

I.E you issued (for example)

> cvs remove -f sheep.php

But not issued

> cvs commit -m removed sheep.php

I've heard work arounds such as:
  • Edit the "entries" file in the relevant CVS directory in your workspace, removing the reference to the file.
    This makes the file appear unknown to CVS.
  • Perform an update in that directory. This gets the repository version of the file and updates the "entries"
    file correctly


All you actually need to do is re-add the file:

> cvs add sheep.php

U sheep.php
cvs server: sheep.php, version 1.6, resurrected

When used in this way, the add command will issue an update against the file and retrieve the repository version of the file.

A word of warning though, if you had uncommitted changes in that file before you issued a remove, CVS isn't going to recover that for you...

How about if you've removed a file, but your version of the file is out of date and so you can't commit it?

So you've issued the following:

> cvs remove -f sheep.txt

cvs server: scheduling 'sheep.txt' for removal
cvs server: use 'cvs sheep' to remove this file permanently

> cvs commit -m removed sheep.txt

cvs server: Up-to-date check failed for 'sheep.txt'
cvs server: correct above errors first!

You can't issue an update because you get the following:

> cvs update sheep.txt

cvs server: conflict: removed sheep.txt was modified by second party
C rob_tmp.txt

Again, add the file.

> cvs add sheep.php

U sheep.php
cvs server: sheep.php, version 1.6, resurrected

This gets you the most up to date version from the repository, that you can then check for changes (you wouldn't want to just remove it now that someone's added new content would you?)

Once you've convinced yourself that it's still a good idea to delete it, just issue the remove and commit.

Simple when you know how!

Can a change in execution plan change the results?

Thu, 2007-07-12 08:15
We've been using Oracle Domain indexes for a while now in order to search documents to get back a ranked order of things that meet certain criteria. The documents are releated to people, and we augment the basic text search with other filters and score metrics based on the 'people' side of things to get an overall 'suitability' score for the results in a search. Without giving too much away about the business I work with I can't really tell you much more about the product than that, but it's probably enough of a background for this little gem. We've known for a while that the domain index 'score' returned from a 'contains' clause is based not only on the document to which that score relates, but also on the rest of the set that is searched. An individual document score does not live in isolation, rather in lives in the context of the whole result set. No problem. As I say, we've known this for a while and so have our customers. Quite a while ago they stopped asking what the numbers mean and learned to trust them. However, today we realised something. Since the results are affected by the result set that is searched, this means that the results can be affected by the order in which the optimizer decides to execute a query. I can't give you a full end to end example, but I can assure you that the following is most definately the case on one of our production domain indexes (names changed, obviously): We have a two column table 'document_index', which contains 'id' and 'document_contents'. Both columns have an index. The ID being the primary key and the other being a domain index. The following SQL gives the related execution path: SELECT id, SCORE( 1 ) FROM document_index WHERE CONTAINS( document_contents, :1, 1 ) > 0 AND id = :2 SELECT STATEMENT TABLE ACCESS BY INDEX ROWID SCOTT.DOCUMENT_INDEX DOMAIN INDEX SCOTT.DOCUMENT_INDEX_IDX01 However, the alternative SQL gives this execution path: SELECT id, SCORE( 1 ) FROM document_index WHERE CONTAINS( document_contents, 'Some text', 1 ) > 0 AND id = :2 SELECT STATEMENT TABLE ACCESS BY INDEX ROWID SCOTT.DOCUMENT_INDEX INDEX UNIQUE SCAN SCOTT.DOCUMENT_INDEX_PK Normally, this kind of change in execution path wouldn't be a problem. But as stated earlier, the result of a score operation against a domain index is not just dependant on the individual records, but the context of the whole result set. The first execution provides you a score for the single document in the context of the all the documents in the table, the second gives you a score within the context of just that document. The scores are different. Now obviously, this is an extreme example, but more subtle examples will almost certainly exist if you combine the domain index lookups with any other where clause criteria. This is especially true if you're using literal values instead of bind variables in which case you may find the execution path changing between calls to the 'same' piece of SQL. My advice? Well, we're going to split our domain index look ups from all the rest of the filtering criteria, that way we can prepare the set of documents we want the search to be within and know that the scoring algorithm will be applied consistently.

Handy "Alert Debugging" tool

Wed, 2007-07-04 13:29
One of the coolest things about OO Javascript is that methods can be written to as if they are variables. This means that you can re-write functions on the fly. Bad for writing maintainable code if you're not structured; Fantastic for things like MVC controllers (rather use the controller to forward calls on to the model, you use it to rewire the view so that it calls it directly, and all without the view even realising it!). What I didn't realise was that the standard window object (and probably so many others out there) can have its methods overwritten like any other. Probably the simplest example of that proves to be incredibly useful... changing the alert function so that the dialog becomes a confirm window. Clicking cancel means that no further alerts are shown to the user. Great for when you're writin Javascript without a debugger and have to resort to 'alert debugging'.

window.alert = function(s) {
if( !confirm(s) ) window.alert = null;
}
In case you're wondering... I found it embedded in the comments on this post: http://www.joehewitt.com/blog/firebug_for_iph.php. Cheers Menno van Slooten

Tab Complete in Windows

Tue, 2007-06-26 14:00
Another one of those things that I can never remember off the top of my head so find myself constantly looking it up whenever I get access to a new machine.

I figure it may as well be my own site that I get the info from :-)

To switch on 'Tab Complete' in Windows command line change the following registry keys to '09':
  • HKEY_LOCAL_MACHINE\Software\Microsoft\Command Processor\CompletionChar
  • HKEY_LOCAL_MACHINE\Software\Microsoft\Command Processor\PathCompletionChar

Haiku

Fri, 2007-06-22 11:54
Saw a cracking Haiku on a t-shirt the other day:

Haiku are easy
But sometimes they don't make sense
Refridgerator.

Then my mind started dwelling on it:

Got the release out
But the testing's not finished
It's falling over

Or

Database is slow
Just can't see what's wrong with it
Set autotrace on

Or

A quick refactor
Turns into a bigger job
Should have unit tests

Records

Mon, 2007-05-28 11:45
And to follow on from the last post... my current personal bests:

I figure if I keep them here, at least I'll always know where they are!
5km Run23:44 (Battersea Park, 'Beat the Baton' 28/05/07)
10km Run53:23 (Hyde Park, 'Run London' 08/10/06)
Half Marathon2:17:49 (Redcar, 'Tees Valley Half Marathon' 12/03/06)
Rubik's cube57 seconds

Targets

Mon, 2007-05-28 11:12
You've gotta have targets.

The more I try to motivate myself to do things, the more I realise that if I don't have a target it's incredibly difficult.

When I realised this it came as a big surprise to me. I'm really not the sort of person to have a 5 year plan or career goals, but it seems that if I don't set myself an only just achievable goal I find it very difficult to motivate myself to do much.

I keep myself fit so that I get the most out of playing football. But just having that in mind isn't enough to get me out and running. If I didn't set myself a target time for a 5km or 10km run and then book a place at a running event, then I'd just sit on my fat arse every night watching TV. OK, so I may be exaggerating my self deprecation, but you get the idea.

I find that this affects me in many different aspects of my life.

To motivate myself to run I set a target (public) 5km or 10km time (this year it's 22:30 and 50:00 respectively).

To motivate myself to learn to do the Rubik's cube, I set myself a target completion time (1 minute - yup, managed it).

To motivate myself to save money I set a target amount to reach by a certain date (nope, not telling you how much).

A friend of mine decided that he'd set himself the target of taking a photo a day for a year and posting it on his site. I may have to steal that idea next year... but until then you can find his here: www.ysr23.com/blog. It really is damn good.

I do the job I do because I just flat out enjoy it. As soon as it becomes too much of a chore I'll move on. And I reckon I'm doing alright career wise in whatever way you choose to measure it. For me the only measure that truly counts is enjoyment, and in the main it's a damn fine job. Well, it is most of the time anyway ;-)

Someone at work once said to me: You know, every now and again Tom Cruise probably gets up in the morning, probably on set, in his trailer and thinks to himself "Damn, gotta do some of that acting shit again today". OK, so he gets paid more in a minute that I do in a year, but you get the point.

And the big thing that keeps my enjoying my job is that I'm still learning new things. I suppose I have a clear target in my career to always keep on learning and to surround myself in people who can teach me. It's probably one of the biggest reasons why I'm so pleased to be working with Extreme Programming. It makes it easy to fulfill that goal. And it works on a clear system of easy to understand targets.

A release to the business has a target set of functionality.
A single story has a clearly defined purpose.
A unit test gives you a goal that must be met, and a clear way of determining the success or failure.

Layers of targets.

And if you're doing XP properly you get to celebrate when you meet those targets.

A brief whoop when the unit test passes.
A handful of jelly beans when the story's complete.
A damn big meal and a piss up when a release hits the business.

OK, so real life targets don't have quite the same level of celebration, but it's the same deal.

Set yourself a clear target and you get clarity of purpose in aiming for it, and the celebration when you pass it.

Roll-out

Wed, 2007-04-11 02:12
I'm pretty sure that most people that read this blog will also read The Daily WTF.

But just in case you don't, there's a nice entry on 'soft-coding'.

Overall the article makes sound sense, but there's a line right at the end that resonates with me, especially since I read it the day after someone told me that they needed a developer for a whole day (9 hours) to roll out their system...

With the myriad of tools available today, there is no reason that your deployment process need be any more complicated than a simple, automated script that retrieves the code from source control, compiles it, copies/installs the executables, and then runs the relevant database scripts.


It makes me feel like I'm not alone.

Question

Fri, 2007-03-23 02:40
I've had this conversation a couple of time with people, and I've realised that I can't get to a satisfactory answer without some research. And I'm lazy. So I'm going to pose a question... and if I don't get a satisfactory answer here I might well send it to The New Scientist in the hope that they'll answer it.

Assuming that the cost of setting up and maintaining the infrastructure is already taken care of, which is more energy efficient: an electric kettle or a stove top kettle?

I am still here...

Sat, 2007-02-17 06:03
Sorry people, I promise I'm still here and I WILL get round to finishing my text on estimating and answering the request for more info on the database patch runner. I will, I will, I will!

The problem is, I've started reading again, and I've started playing on-line poker. Damn it :-)


But I'm enjoying it, especially a Cohn book on Agile Estimation and Planning. It is an absolute MUST read. It takes off where the estimation chapter from User Stories Applied left off, and it really doesn't dissappoint.

Unfortunately it seems to say an awful lot that I agree with, and was going to form the bulk of my next couple of posts. So if you like what I have to say on the topic, then Mike Cohn is definately worth a read... he goes into a lot more detail than I ever will here!

Obviously I'm reading an awful lot on Texas Hold 'em as well... but I'm not going to tell you what 'cause that might take away my advantage ;-)

Producing Estimates

Sun, 2007-01-07 07:52
OK, so it's about time I got back into writing about software development, rather than software (or running, or travelling, or feeds) and the hot topic for me at the moment is the estimation process.

This topic's probably a bit big to tackle in a single post, so it's post series time. Once all the posts are up I'll slap another up with all the text combined.

So – Producing good medium term estimates...

I'm not going to talk about the process for deriving a short term estimate for a small piece of work, that's already covered beautifully by Mike Cohn in User Stories Applied, and I blogged on that topic some time ago. Rather I'm going to talk about producing an overall estimate for a release iteration or module.

I've read an awful lot on this topic over the last couple of years, so I'm sorry if all I'm doing is plagiarising things said by Kent Beck, Mike Cohn or Martin Fowler (OK, the book's Kent as well, but you get the point), or any of those many people out there that blog, and that I read. Truly, I'm sorry.

I'm not intending to infringe copyright or take credit for other people's work, it's just that my thinking has been heavily guided by these people. This writing is how I feel about estimating, having soaked up those texts and put many of their ideas into practice.

Many people think that XP is against producing longer term estimates, but it isn't. It's just that it's not about tying people down to a particular date 2 and a half years in the future and beating them with a 400 page functional design document at the end of it; it's about being able to say with some degree of certainty when some useful software will arrive, the general scope of that software, and ultimately to allow those people in power to be able to predict some kind of cost for the project.

Any business that allows the development team to go off and do a job without providing some kind of prediction back to the upper management team being irresponsible at best, grossly negligent at worst.

Providing good medium term estimates is a skill, and a highly desirable one. By giving good estimates and delivering to them you are effectively managing the expectations of upper management and allowing them to plan the larger scale future of the software in their business. When they feel they can trust the numbers coming out of the development teams it means they are less likely to throw seemingly arbitrary deadlines at their IT departments and then get angry when they're not met. Taking responsibility for, and producing good estimates will ultimately allow you to take control of the time-scales within your department. If you continually provide bad estimates or suggest a level of accuracy that simply isn't there by saying "it'll take 1,203 ½ man days to complete this project", then you've only got yourself to blame when that prediction is used to beat you down when your project isn't complete in exactly 1,203 ½ man days.

Whilst being written within the scope of XP, there's no reason why these practices won't work when you're not using an agile process. All you need to do is to split your work into small enough chunks so that each one can be estimated in the region of a few hours up to 5 days work before you start.

In summary, the process is this:
  • Produce a rough estimate for the whole of the release iteration.
  • Iteratively produce more detailed estimates for the work most likely to be done over the next couple of weeks.
  • Feed the detailed estimates into the overall cost.
  • Do some development.
  • Feed the actual time taken back into the estimates and revise the overall cost.
  • Don't bury your head in the sand if things aren't going to plan.


1 – Produce a rough estimate for the whole of the release iteration.

Before you can start work developing a new release you should have some idea of what functionality is going into that release. You should have a fairly large collection of loosely defined pieces of functionality. You can't absolutely guarantee that these stories will completely form the release that will go out in 3 months time, but what you can say is: "Today we believe that it would be most profitable for us to work on these areas of functionality in order to deliver a meaningful release to the business within a reasonable time-frame".

Things may change over the course of the next few months, and the later steps in this process will help you to respond to those changes and provide the relevant feedback to the business.

Kent Beck states (I paraphrase): You don't drive a car by pointing it at the end of the road and driving in a straight line with your eyes closed. You stay alert and make corrections moment by moment.
I state: When you get in a car and start to drive you should at least have some idea where you're going.

The two statements don't oppose each other.

The basic idea is this:
  • In broad strokes, group the stories in terms of cost in relation to each other. If X is medium and Y is huge then Z is tiny.
  • Assign a numbered cost to each group of stories.
  • Inform that decision with past experience.
    Produce a total.


So, get together the stories that you're putting into this release iteration, grab a room with a big desk, some of your most knowledgeable customers and respected developers and off you go.

Ideally you want to have around 5 to 8 people in the room, more than this and you'll find you end up arguing over details, less and you may find you don't have enough buy in from the customer and development teams.

As a golden rule: developers that are not working on the project should NOT be allowed to estimate. There's nothing worse for developer buy-in than having an estimate or deadline over which they feel that have no control.

Try to keep the number of stories down, I find around 50 stories is good. If you have more you may be able to group similar ones together into a bigger story, or you may find you have to cull a few. That's OK, you can go through this process several times. You can try to go through the process with more, but I find that you can't keep more than 50 stories in your head at one time. You're less likely to get the relative costs right. And it'll get boring.

Quickly estimate each story:
  • The customer explains the functionality required without worrying too much about the about the detail;
  • The developers place each story into one of 4 piles: small, medium, large and wooooaaaah man that's big.


People shouldn't be afraid to discuss their thinking, though you should be worried if it's taking 10 minutes to produce an estimate for each story.

You may find that developers will want to split stories down into smaller ones and drive out the details. Don't, if you can avoid it. At this point we want a general idea of the relative size of each story. We don't need to understand the exact nature of each individual story, we don't need enough to be able to sit down and start developing. All we need is a good understanding of the general functionality needed and a good idea of the relative cost. Stories WILL be re-estimated before they're implemented and many of them will be split into several smaller ones to make their development simpler. But we'll worry about that later.

As the stories are being added to piles be critical of past decisions. Allow stories to be moved between piles. Allow piles to be completely rebuilt. You may start off with 10 stories that spread across all 4 piles, then the 11th 12th and 13th stories come along and have nowhere to go – they're all an order of magnitude bigger than the ones that have gone before. That's OK, look at the stories you've already grouped in light of this new knowledge and recalibrate the piles.

Once all the stories are done, spread the piles out so you can see every story in each one. Appraise your groupings. Move stories around. It's important that you're comfortable that you've got them in the right pile relative to each other.

If the developers involved in this round of estimating recently worked on another project or a previous release of this project then add some recently completed stories from that work. Have the developers assign those stories into the piles. You know how long those stories took and you can use that to help guide your new estimates. There's nothing more useful in estimating than past experience... don't be afraid to use that knowledge formally.

Once you're that the piles are accurate, put a number of days against each pile. The idea is to get 'on average a single story in this pile will take x days'.

If you have to err, then err on the side of bigger. Bear in mind that people always estimate in a perfect world where nothing ever goes wrong. The stories you added from the last project can be used to guide the number. You know exactly how long it took to develop those stories and you'd expect the new numbers to be similar.

The resulting base estimate is then just the sum of (number of stories in each pile * cost of that pile). This number will give you a general estimate on the overall cost.

You'll probably want to add a contingency, and past experience on other projects will help you guide that. If you've gone through this process before, pull out the numbers from the last release... when you last performed this process and compare the starting estimate with the actual amount of time taken. Use that comparison for the contingency.

The gut feeling is to say, "Hang on, the last time we did this we estimated these 50 stories, but only built these 20 and added these other 30. That means that the starting estimate was nothing like what we actually did". But the point is that if every release has the same kind of people working on it, working for the same business with the same kinds of pressures then this release is likely to be the same as the last. Odds are that THIS release will only consist of 20 of these stories plus 30 other unknown ones... and the effect on the estimate is likely to be similar. Each release is NOT unique, each release is likely to go ahead in exactly the same way as the last one. Use that knowledge, and use the numbers you so painstakingly recorded last time.

Aside: Project managers tend to think that I have a problem with them collecting numbers (as they love to do). They're wrong... I have a problem with numbers being collected and never being used. The estimation process is the place where this is most apparent. Learn from what happened yesterday to inform your estimate for tomorrow.


Once the job's done you should have enough information to allow you to have the planning game. For those not familiar with XP, that is the point at which the customer team (with some advice from the development team) prioritises and orders the stories. It gives you a very good overall view of the direction of the project and a clear goal for the next few weeks of work.

At this point you should have a good idea of cost and scope and have a good degree of confidence in both. Now's the time to tell your boss...

Next up – using the shorter term estimates to inform the longer term one...